1998 MARS SURVEYOR PROJECT STATUS REPORT
December 21, 1998John McNamee
Mars Surveyor 98 Project ManagerMars Polar Lander: Launch -13 days
The lander was transported to Space Launch Complex 17B (SLC-17B) at 3:00 am EST Monday morning as scheduled and mated with the Delta stack. A full functional checkout (T-7) of the science payload was completed successfully. A full functional checkout of the lander's engineering subsystems, both "A" and "B" strings, is progressing nominally and is scheduled for completion Tuesday.
Addendum by Ron Baalke:
The following WebCams are now available for the Mars Polar Lander, showing launch preparation activities at Launch Pad 17B:
http://mars.jpl.nasa.gov/msp98/lander/ksc.html (still images)
http://mars.jpl.nasa.gov/msp98/lander/ksc1.html (video stream)
http://mars.jpl.nasa.gov/msp98/lander/ksc2.html (still images)
http://mars.jpl.nasa.gov/msp98/lander/ksc3.html (video stream)
Time Lapse Movie
Mars Polar Lander Spacecraft At Kennedy Space Center
December 21, 1998
Mars Polar LanderMPEG Movie - 2.0 MB Need help in running animations? Look here for information on how to setup your browser for animations.