1998 MARS SURVEYOR PROJECT STATUS REPORT
December 11, 1998John McNamee
Mars Surveyor 98 Project ManagerThe orbiter was launched successfully at 1:45 pm EST on Friday December 11.
Lander launch processing activities are proceeding on schedule in the Spacecraft Assembly and Encapsulation Facility (SAEF-2) at Kennedy Space Center (KSC) with launch vehicle 3rd stage mate 6 days away and launch 23 days away. Hydrazine was loaded on the vehicle. Final planetary protection assays were taken. Cruise stage solar arrays and the heat shield were installed. Spin balance was completed.