1998 MARS SURVEYOR PROJECT STATUS REPORT
December 1, 1998John McNamee
Mars Surveyor 98 Project ManagerMars Climate Orbiter: Launch -9 Days
The orbiter battery was charged and the T-7 functional test was performed successfully.
Mars Polar Lander: Launch - 33 Days
The JPL Director's Mission Readiness Review and Lockheed Martin Astronautics (LMA) President's Review were conducted. Flight Software (FSW) Build 8.2 was loaded on the lander. An additional 2 days of margin were identified in the Boeing post-mate flow and a tentative agreement has been reached to allocate that as added spacecraft margin by delaying the mate to December 17.
Time Lapse Movie
Mars Surveyor 98 Spacecraft At Kennedy Space Center
December 1, 1998
Mars Climate Orbiter
MPEG Movie - 3.0 MB
Mars Polar Lander
MPEG Movie - 668K
Need help in running animations? Look here for information on how to setup your browser for animations.
Home Mars Polar Lander Deep Space 2 Microprobes Mars Climate Orbiter Welcome Mailing List Links Credits For questions or comments on this website please refer to our list of contacts.