1998 MARS SURVEYOR PROJECT STATUS REPORT
November 22, 1998John McNamee
Mars Surveyor 98 Project ManagerMars Climate Orbiter: Launch -18 Days
Final closeout activities are progressing on schedule. Flight Sofware (FSW) patch 8.2.1.D was loaded and the spacecraft was powered down for the final time until the F-7 functional test on the Delta stack at SLC-17A on December 1.
Mars Polar Lander: Launch - 42 Days
The parachute and mortar were installed but final mate was not accomplished due to a mismatch between mortar and flight connector.
The Bonum spacecraft was launched on a Delta at 7:00 pm - this clears launch pad 17B for the lander - no other Delta launches occur before the Mars Climate Orbiter on December 10.
Time Lapse Movie
Mars Surveyor 98 Spacecraft At Kennedy Space Center
November 22, 1998
Mars Climate Orbiter
MPEG Movie - 332K
Mars Polar Lander
MPEG Movie - 1.4 MB
Need help in running animations? Look here for information on how to setup your browser for animations.
Home Mars Polar Lander Deep Space 2 Microprobes Mars Climate Orbiter Welcome Mailing List Links Credits For questions or comments on this website please refer to our list of contacts.