1998 MARS SURVEYOR PROJECT STATUS REPORT
November 18, 1998John McNamee
Mars Surveyor 98 Project ManagerMars Climate Orbiter: Launch -22 Days
Battery conditioning (cycle #2) was completed. Final closeout activities are progressing on schedule.
Mars Polar Lander: Launch -46 days
Flag closure/data review day. The re-re-worked flight Pyro Initiation Unit (PIU) was received at Kennedy Space Center and will be installed on the lander tomorrow.
Time Lapse Movie
Mars Polar Lander Spacecraft At Kennedy Space Center
November 18, 1998
Mars Polar LanderMPEG Movie - 3.3 MB Need help in running animations? Look here for information on how to setup your browser for animations.