1998 MARS SURVEYOR PROJECT STATUS REPORT
November 10, 1998John McNamee
Mars Surveyor 98 Project ManagerMars Climate Orbiter: Launch -30 Days
The cruise/TCM (Trajectory Correction Maneuver) MST (Mission Systems Test) was run successfully - this completes the planned sequence verification testing on the orbiter vehicle. Power on/stray voltage testing and the final ordance electrical mate was completed. The JPL Director's Mission Readiness/LMA (Lockheed Martin Astronautics) President's Reviews were conducted in Denver - the orbiter received a "thumbs up" for launch.
Mars Polar Lander: Launch - 54 Days
Sep nut torque validation activities were conducted. The DS2 (Deep Space 2) microprobes were preped for installation on the lander cruise stage.
Time Lapse Movie
Mars Surveyor 98 Spacecraft At Kennedy Space Center
November 10, 1998
Mars Climate Orbiter
MPEG Movie - 3.5 MB
Mars Polar Lander
MPEG Movie - 1.9 MB
Need help in running animations? Look here for information on how to setup your browser for animations.
Home Mars Polar Lander Deep Space 2 Microprobes Mars Climate Orbiter Welcome Mailing List Links Credits For questions or comments on this website please refer to our list of contacts.