1998 MARS SURVEYOR PROJECT STATUS REPORT
November 3, 1998John McNamee
Mars Surveyor 98 Project ManagerMars Climate Orbiter: Launch -37 days
Flight software build 8.2.1 was loaded on the orbiter and the star camera portion of the Attitude Control System (ACS) phasing test was completed successfully. The reaction wheel phasing is scheduled for completion tommorrow.
Mars Polar Lander: Launch -61 days
The Deep Space Network (DSN) End-to-End compatibility test was completed with no spacecraft issues and no significant ground configuration issues.
Time Lapse Movie
Mars Surveyor 98 Spacecraft At Kennedy Space Center
November 3, 1998
Mars Climate Orbiter
MPEG Movie - 4.1 MB
Mars Polar Lander
MPEG Movie - 581K