1998 MARS SURVEYOR PROJECT STATUS REPORT
October 31, 1998John McNamee
Mars Surveyor 98 Project ManagerPyro Initiation Unit (PIU) ATLO Test Unit (ATU) troubleshooting was successfully completed. The previously observed failure was duplicated on the vehicle and the data captured. Belief is that the ATU contains a defective part. The ATU was removed and returned to Denver for analysis and the reworked flight PIU was reinstalled on the orbiter. The reworked flight PIU functions and interfaces were retested and reverified successfully on the orbiter.
The Attitude Control System (ACS) phasing test was partially completed with several issues regarding the star camera to be resolved. The launch/init mission system test was conducted successfully. The star camera issues discovered were determined to be caused by incorrect paramaters in the lander database. The star camera portion of the ACS phasing will be repeated next week.
Time Lapse Movie
Mars Surveyor 98 Spacecraft At Kennedy Space Center
October 31, 1998
Mars Climate Orbiter
MPEG Movie - 2.5 MB
Mars Polar Lander
MPEG Movie - 601K
Need help in running animations? Look here for information on how to setup your browser for animations.
Home Mars Polar Lander Deep Space 2 Microprobes Mars Climate Orbiter Welcome Mailing List Links Credits For questions or comments on this website please refer to our list of contacts.