Mars Polar Lander Mars Volatiles and Climate Surveyor (MVACS) Lidar and Mars Microphone Mars Descent Imager (MARDI) Deep Space 2 Microprobes Deep Space 2 Microprobes Jet Propulsion Laboratory NASA Images, Images, Images Current Mission Status & News What We Hope To Learn Our Mission Mars Exploration Comments Or Questions? To Find Your Way Around Mars Polar Lander Mars Polar Lander

1998 MARS SURVEYOR PROJECT STATUS REPORT
October 22, 1998

John McNamee
Mars Surveyor 98 Project Manager

Mars Climate Orbiter: Launch -49 Days

ATLO Test Unit (ATU) Pyro Intitiation Unit (PIU) troubleshooting activities were conducted. Installed Multi-Layer Insulation (MLI) on propulsion module.

Mars Polar Lander: Launch -73 days

Thermal enclosure closeout was completed. Flight batteries were charged.

Time Lapse Movie

Mars Surveyor 98 Spacecraft At Kennedy Space Center
October 22, 1998


Mars Climate Orbiter
MPEG Movie - 3.5 MB

Mars Polar Lander
MPEG Movie - 901K
Need help in running animations? Look here for information on how to setup your browser for animations.


Home Mars Polar Lander Deep Space 2 Microprobes Mars Climate Orbiter
Welcome Mailing List Links Credits

For questions or comments on this website please refer to our list of contacts.